What independent witness testing of new or modernised Lifts, escalators and moving walks involves, which tests are witnessed, and how it protects the owner at handover.

What is Lift, escalator and moving walk witness testing? Independent observation of a new or modernised unit's safety tests before handover, on the owner's behalf. Also a defect inspection on installation defects can be undertaken.
Want an independent view of your own lifts?
Talk to a consultantBefore a new or modernised Lift, escalator or moving walk carries its first passenger, it must pass a series of safety tests. The installer does the tests, so it matters who watches them.
In independent witness testing, a consultant acting for the owner is present for the critical tests, checks the results and signs off only when the equipment is right. It is one of the cheapest protections an owner can buy.
Witness testing is the independent observation of the commissioning tests carried out before handover. The consultant checks that each test is done correctly, that the results meet the relevant standards and the specification, and that the paperwork is complete.
LML's consultants include engineers who spent decades commissioning vertical transport for the major manufacturers, where their job was to make sure equipment was tuned, tested and safe before handover.
LML witnesses the critical safety tests before handover, including fire service operation where it is fitted. The witnessed tests usually include:
Problems of the kind witness testing exists to catch include governors set outside the required range, door protection that does not detect small objects, and emergency phones that have not been connected.
The installer is motivated to fix things quickly while handover and final payment are still to come. After that, every fix is harder to get.
Witness testing is written into the technical specification, so the installer programmes for it and the owner's consultant attends. It takes place between practical completion and handover, and the defects liability period follows. See Defects liability period: what to check.
A failed test means the process is doing its job. The installer fixes the fault, the test is repeated and witnessed again, and the result is recorded. Handover should wait until every critical test has passed, while items that don't affect safety can go on a defects list with agreed completion dates.
Plan for these people to be present:
At the end of witness testing, the owner should hold:
Test results should be supplied in writing at handover, because records sent later are easy to lose and hard to chase.
Independent observation of a new or modernised unit's safety tests before handover, on the owner's behalf.
Independent witnessing isn't always a legal requirement. Registration processes often rely on the contractor's test results at handover, and witnessing gives the owner independent assurance that the tests relied on were done properly.
Allow roughly half a day to a day per Lift, escalator or moving walk depending on the tests and if any issues are identified that require immediate rectification.
LML Lift Consultants specifies, witnesses and signs off Lift, escalator and moving walk testing on new installations and modernisations.